18.100.100 Approval of final plat.
This section is included in your selections.
The commission shall approve or reject the final plat within 60 days from the date of filing, after public notice, unless the time is extended by agreement with the subdivider. Reasons for rejection shall be limited to failure to implement the terms of the preliminary plat approval or final plat requirements, and stated in the minutes of the meeting. A copy thereof shall be supplied to the subdivider.